India recorded a power supply shortage of 1,201 million units in October 2021 — the highest in 5.5 years — due to a crunch in coal stocks availability at thermal plants.
About:
The shortage was mostly restricted to Gujarat, Haryana, Jharkhand, Punjab and Rajasthan.
In October, Gujarat recorded a power shortage of 215 million units, the highest for any month in more than a decade. With a shortage of 77 million units, Jharkhand too recorded its highest deficit in more than a decade.
Supply shortage was also observed in Uttar Pradesh and the Union Territory of Jammu and Kashmir in October, however, they were not an anomaly but were similar to the general trend observed in the regions.
The power shortage was primarily due to a supply crunch of coal to 135 thermal plants. As on November 5, the average coal inventory held by the plants would last only seven days.
Historical data were compiled from the Central Electricity Authority, and October 2021 data were compiled from day-wise reports available with the National Load Despatch Centre (NLDC) under the Ministry of Power.
Dear Student,
You have still not entered your mailing address. Please enter the address where all the study materials will be sent to you. (If applicable).